This is a goal set out by the Southern Electricity Company. Accordingly, the company has launched a project of enhancing energy efficiency in Binh Duong rural areas since Feb. 2013. The project will install 53.2km of middle voltage power lines, 90.3km of lower voltage lines, 97km of transformer stations with the total capacity of 15,288kVA. The total value of the project is at VND53.6bil.
In 2012, Binh Duong Electricity Company received 41 works middle and lower voltage power lines and 47 transformer stations with the capacity of 14,980kVA. At present, 100% of communes, wards and townships in the locality have connected with the national grid.
Reported by M.Nguyen – Translated by A.C