In 2014, Phu Giao District has carried out 22 new constructions. During the year, Phu Giao finalized and put into use 17 constructions, reaching 77.2% of the year plan including 3 office buildings, 1 cultural and social building, 6 educational works, 6 transportation and traffic projects and 1 for public healthcare. Compared with the capital allocation for the construction of VND 142 billion, the actual implemented volume is more than VND 268.9 billion, or 189.26% of the capital allocation plan; allocated value reached VND 126.7 billion, or 89.2% of the capital allocation plan.
Besides, in 2014, Phu Giao District completed verification procedures, and approval of the settlement for 14out of 26 projects forwarded from previous stage. Currently there are 12 district projects pending for completion of settlement documents and audit.
Reported by H.Phuong – Translated by Vi Bao