Positive signal of capital disbursement
Improving public investment efficiency is one of 3 main issues of economic reform triangle. Especially, when repercussion of basic construction capital to curb inflation remains existent, how to allocate capital to needed projects and create a good infrastructure for local socio-economic development are very important issues.
Notably, Di An town has well implemented these issues. According to the town management board, the town’s capital disbursement plan 2013 is at VND293.7bil. In the first quarter of this year, the town disbursed VND94.1bil, winning 32% from its plan. This result is a positive signal in implementing the town basic construction investment.
According to the town People’s Committee chairman Vo Van Minh, owing to decrease on basic construction capital allocation, the town has focused on projects in need.
Priorities for key works
Reportedly, in the first quarter of 2013, there are now 17 projects in preparation for investment, 11 ones waiting for approval, 38 ones underway and so on.
To hasten progress of the projects, the town People’s Committee has focused on implementing site clearance. At present, some projects remain shortcomings relating to compensation and site clearance. They include Chieu Lieu – Binh Tri road project, Tan Quy Temple road, Tan Binh-Tan Dong Hiep road, Ho Lang relic site.
Minh added that to win efficiency on public investment, the town administration will concentrate on giving priorities of capital for key works in an attempt to solve urgent demand and impetus local socio-economic development.
Accordingly, there are 8 key works including Thong Nhat primary school, Thong Nhat pre-school, Nguyen Thuong Hien high school, Di An town medical center, Binh Thang ward administration area and among others.
Reported by T.Son – Translated by A.C