Hastening key works’ progress


Work of Binh Duong hospital of Tuberculosis and Lung diseases.

In order to complete 2015’s plan, Binh Duong has focused on hastening progress of key works, contributing to perfect infrastructure structure and meet local residents’ real demand as well as spur socio-economic development.

Hastening progress

Nguyen Chi Duc, vice director of the provincial project management board of construction and investment said that as of March 16, 2015 completion of this year’s projects reached 28.62% with value of capital of about VND540.591bn, winning 39%.

In 2015, the provincial project management board of construction and investment is assigned to invest in 56 projects under the State budget, 23 of which are underway. They include Bung Biep-Suoi Cat Spring water drainage canal, Phu Hoa resettlement area, Ba Lua Bridge, Ong Co Bridge and more.

In addition, 5 other projects are under assessment, 5 under design phase, 3 under compensation and site clearance. As for lottery capital source, the provincial project management board of construction and investment is assigned to invest in 13 projects, 4 of which are under construction, 1 under tender, 3 under design, 1 under assessment and 1 under compensation and site clearance.

As planned, Binh Duong will in the second quarter of this year complete and put into use projects and works such as upgrading and extending DT747 road from Ba Nghia to Cong Xanh; newly building Ba Lua Bridge; constructing a road along to Sai Gon River; upgrading and extending DT744 road and more.

Rep of contractor of road along to Sai Gon River from Binh Nham to Chau Van Tiep said that as of the first quarter of this year the project’s 1st phase was perfected. At present, the contractor has built stone dyke along to the road.

Meanwhile, the project of upgrading and extending DT747A road from Ba Nghia to Cong Xanh includes 3 packages. The 1st package (Km16+717 to Km19+638,37) was completed about 62% of volume. In addition, the third package reached about 69.61% of volume.

Moreover, projects invested from lottery capital source are hastened their progress. Accordingly, project of 1,500-bed general hospital is underway while Binh Duong hospital of Tuberculosis and Lung diseases starts construction of important items. Once put into operation, these projects will contribute to meet local residents’ demand on healthcare.

Ensuring completion of plans

In order to complete progress of works as the set plans, the provincial project management board of construction and investment will continue to work with relevant units to spur inspection of construction volume in a bid to hasten disbursement of works. In addition, the provincial project management board of construction and investment will cooperate with centers of land fund development to hasten progress of site clearance and resettlement for pending projects.

Nguyen Chi Duc added that the provincial project management board of construction and investment will in the coming time hold inspections of works underway, assure quality and time of projects.

Besides, the provincial project management board of construction and investment will focus on building newly projects such as the provincial hospital of Rehabilitation, 300-bed maternity ward treatment area under the provincial general hospital, Children’s Hospital and among others.

Furthermore, the provincial project management board of construction and investment will concentrate on solving problems of investment procedures, design adjustment as well as hastening progress of project assessment, report of technical economy to soon transfer implementation phase.

Reported by P.Le – Translated by A.C

Tags: key works

Green development under local characteristics

With various industrial parks (IPs) already built or planned for future investment, Bau Bang district has identified green industry as its strategic path

Vietnamese products grab spotlight at Algiers int’l fair 2025

Vietnamese goods are gaining international attention at the 56th Algiers International Fair (FIA 2025), held from June 23–28 in Algeria's capital.

OCOP programme hits milestone with 126 five-star products nationwide

The National Council for the Evaluation of OCOP Products on Tuesday announced the recognition of 47 new five-star-rated products under the One Commune One Product (OCOP) programme,

In-depth industrial development

In the first six months of 2025, the Index of Industrial Production (IIP) in Binh Duong province is estimated at increasing by 10.19% compared to the same period last year.

In-depth industrial development

In the first six months of 2025, the Index of Industrial Production (IIP) in Binh Duong province is estimated at increasing by 10.19% compared to the same period last year.

Establishing a framework for the reorganization of the global supply chain

In light of the global economy being influenced by various factors such as supply chain disruptions,

Opening doors for workers to own housing

With the strong support of the government, active participation from the banking system, and the attention of provincial leaders and businesses, access to social housing for workers and low-income individuals is widening.

Tan Uyen city enhances the inspection and enforcement of trade violations

In accordance with the directives of the Provincial Steering Committee for the Prevention of Smuggling, Trade Fraud,

Total tax revenue in Binh Duong reaches 63.7% of estimate

On June 23, Tax Department of Region XVI held a conference to review tax work for the first six months of 2025, outline tasks for the remaining six months, and honor exemplary enterprises.

Elevating development

Amid the current global economic landscape, which is being significantly impacted by shifts in supply chains, trade dynamics

Enterprise - Brand

Company Social Media Net

Company VIETNAMNAY

Company HANEL MIROLIN

Company Keangnam - vina

Company HP Travel

Company Keloph