HO CHI MINH ROAD PROJECT SECTION THROUGH BINH DUONG: Striving for early completion

More than 31km of the Ho Chi Minh Road section running through Binh Duong province is currently being accelerated by the construction unit, aiming for technical opening by the upcoming April 30 holiday. However, there are still some construction site problems on this route, along with the lack of land for road leveling, affecting the construction progress. Here are the images of the working atmosphere at the construction site from Binh Duong Newspaper.

Thanh An bridge over the Saigon River is one of six bridges along the Ho Chi Minh Road section through Binh Duong province that has just been completed
The lack of soil for road leveling is one of the main factors affecting the construction progress
Workers are urgently completing the remaining construction items of Thanh An bridge
The construction unit has increased manpower and machinery, working in "three shifts and four teams" to accelerate the project's progress

 

According to the construction unit, in addition to the lack of soil materials for road leveling, the construction package through Binh Duong province still has some locations that have not been handed over the site for construction yet.
The intersection of ​​Ho Chi Minh road with DT744 road through Thanh An commune’s Ben Chua hamlet in Dau Tieng district is under construction
The appearance of the Ho Chi Minh road section passing through Binh Duong province is gradually taking shape

The construction package No. 1 covers the section from Km10+000 to Km40+150, starting at Km10+000 in Bau Bang district’s Tru Van Tho commune in Binh Duong province and ending at Km41+150, adjacent to the Construction Package No. 2 in Trang Bang district’s Hung Thuan commune in Tay Ninh Province. The total length of the route under this package is approximately 31.15 kilometers, with a total contract value of VND 681.84 billion.

Pham Van Hung, Deputy General Director of Deo Ca Group, the contractor for this package stated that the roadbed has been basically completed. Currently, the construction of various sub-base layers is underway, covering 30 out of 31 kilometers and asphalt pavement has been completed on nearly 21 kilometers. The overall progress of the package has reached 70% of the contract value. Deo Ca Group is making great efforts to overcome obstacles and is determined to open the entire route to technical traffic in time for the 50th anniversary of the Liberation of the South and National Reunification (April 30, 1975 – April 30, 2025), shortening the schedule by seven months compared to the original contract.

 Reported by Minh Duy-Cong Khanh-Translated by Kim Tin

Tags: Bau Bang

Advancement noted in transportation infrastructure development

Binh Duong recognizes infrastructure development as a strategic breakthrough and a focal point for socio-economic advancement, particularly in regional transport infrastructure.

PM urges drastic measures to ensure power supply for peak period

It noted that as ensuring national energy security and sufficient electricity supply is one of the fundamental and decisive factors for the successful implementation of the country’s socio-economic growth targets

Vietnam, US kick start bilateral economic, trade negotiations

Vietnamese ministries and sectors stand ready to address the US’s concerns and work together to find mutually beneficial solutions based on the principle of harmonised interests and shared risks

Gov't demands starting work on North – South high-speed railway by end of 2026

Recognising the scale and complexity of this project as unprecedented in Vietnam, the Government has directed relevant ministries, provincial authorities

Agricultural sector enhanced

After over 28 years of development, thanks to effectively tapping its potential and advantages, Binh Duong’s economy has made significant achievements in all fields.

Vietnam targets global Halal market as US tariffs bite

With its ranking among the top 20 global food exporters and top 15 agricultural exporters, bolstered by 17 free trade agreements (FTAs), Vietnam is a strong contender in the global Halal supply chain.

Master plan for Di An city announced and investment promotion launched

Early April 22, Di An city’s Party Committee held a ceremony to announce the city’s master plan and promote investment.

Propelling Binh Duong towards new heights

Fifty years after the South's complete liberation and nearly thirty years of construction and development, with various models implemented throughout each stage

Initiatives to achieve sustainable development objectives

Over three decades of industrial advancement, coupled with policies of “rolling out the red carpet to attract investment”

Vietnam tightens product origin rules to boost global trade edge

As Vietnam deepens its integration into the global economy through more than 15 free trade agreements (FTAs),

Enterprise - Brand

Company Social Media Net

Company VIETNAMNAY

Company HANEL MIROLIN

Company Keangnam - vina

Company HP Travel

Company Keloph