HO CHI MINH ROAD PROJECT SECTION THROUGH BINH DUONG: Striving for early completion

More than 31km of the Ho Chi Minh Road section running through Binh Duong province is currently being accelerated by the construction unit, aiming for technical opening by the upcoming April 30 holiday. However, there are still some construction site problems on this route, along with the lack of land for road leveling, affecting the construction progress. Here are the images of the working atmosphere at the construction site from Binh Duong Newspaper.

Thanh An bridge over the Saigon River is one of six bridges along the Ho Chi Minh Road section through Binh Duong province that has just been completed
The lack of soil for road leveling is one of the main factors affecting the construction progress
Workers are urgently completing the remaining construction items of Thanh An bridge
The construction unit has increased manpower and machinery, working in "three shifts and four teams" to accelerate the project's progress

 

According to the construction unit, in addition to the lack of soil materials for road leveling, the construction package through Binh Duong province still has some locations that have not been handed over the site for construction yet.
The intersection of ​​Ho Chi Minh road with DT744 road through Thanh An commune’s Ben Chua hamlet in Dau Tieng district is under construction
The appearance of the Ho Chi Minh road section passing through Binh Duong province is gradually taking shape

The construction package No. 1 covers the section from Km10+000 to Km40+150, starting at Km10+000 in Bau Bang district’s Tru Van Tho commune in Binh Duong province and ending at Km41+150, adjacent to the Construction Package No. 2 in Trang Bang district’s Hung Thuan commune in Tay Ninh Province. The total length of the route under this package is approximately 31.15 kilometers, with a total contract value of VND 681.84 billion.

Pham Van Hung, Deputy General Director of Deo Ca Group, the contractor for this package stated that the roadbed has been basically completed. Currently, the construction of various sub-base layers is underway, covering 30 out of 31 kilometers and asphalt pavement has been completed on nearly 21 kilometers. The overall progress of the package has reached 70% of the contract value. Deo Ca Group is making great efforts to overcome obstacles and is determined to open the entire route to technical traffic in time for the 50th anniversary of the Liberation of the South and National Reunification (April 30, 1975 – April 30, 2025), shortening the schedule by seven months compared to the original contract.

 Reported by Minh Duy-Cong Khanh-Translated by Kim Tin

Tags: Bau Bang

Concentrating on executing and investing in IPs development under established planning

According to the Binh Duong Industrial Parks Management Board, the Provincial People's Committee

Ensuring public safety against counterfeit goods

Counterfeit goods pose a serious threat, causing a range of negative consequences, including economic losses for businesses, risks to public health and the erosion of consumer trust.

Provincial leaders receive and work with MiTAC Group Chairman

On the afternoon of June 11, Bui Minh Tri, Vice Chairman of provincial People’s Committee received and worked with Su Liang, Chairman of MiTAC Group (Taiwan, China)

Efforts to build a civilized and modern city

With the goal of becoming a key development center in the Southeastern region, Binh Duong province has been actively implementing the local Master Plan for the 2021–2030 period

Bau Bang: Industrial development and effective investment attraction

Industrial development has significantly contributed to the transformation of the socio-economic situation in Bau Bang district.

Project No.06: Numerous benefits for citizens and businesses

The project to develop the application of population data, electronic identification and authentication to serve the National Digital Transformation for the period of 2022–2025,

Building brands, enhancing local products’ value

Through continuous efforts, production units in the province have increasingly strengthened consumers’ confidence in Vietnamese goods in general and local products in particular

Wood industry seeks new export markets

Confronted with unpredictable developments in the export market, businesses, particularly in the wood industry, are striving to implement flexible policies.

Being determined to complete compensation and site clearance for key transportation projects

Mr. Vo Van Minh, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, chaired an online meeting with relevant localities to assess the progress of compensation and site clearance

Banks' bond issuance soars threefold in first five months

During this period, bank bonds constituted 67.1% of the total issuances, overshadowing the real estate sector,

Enterprise - Brand

Company Social Media Net

Company VIETNAMNAY

Company HANEL MIROLIN

Company Keangnam - vina

Company HP Travel

Company Keloph