HO CHI MINH ROAD PROJECT SECTION THROUGH BINH DUONG: Striving for early completion

More than 31km of the Ho Chi Minh Road section running through Binh Duong province is currently being accelerated by the construction unit, aiming for technical opening by the upcoming April 30 holiday. However, there are still some construction site problems on this route, along with the lack of land for road leveling, affecting the construction progress. Here are the images of the working atmosphere at the construction site from Binh Duong Newspaper.

Thanh An bridge over the Saigon River is one of six bridges along the Ho Chi Minh Road section through Binh Duong province that has just been completed
The lack of soil for road leveling is one of the main factors affecting the construction progress
Workers are urgently completing the remaining construction items of Thanh An bridge
The construction unit has increased manpower and machinery, working in "three shifts and four teams" to accelerate the project's progress

 

According to the construction unit, in addition to the lack of soil materials for road leveling, the construction package through Binh Duong province still has some locations that have not been handed over the site for construction yet.
The intersection of ​​Ho Chi Minh road with DT744 road through Thanh An commune’s Ben Chua hamlet in Dau Tieng district is under construction
The appearance of the Ho Chi Minh road section passing through Binh Duong province is gradually taking shape

The construction package No. 1 covers the section from Km10+000 to Km40+150, starting at Km10+000 in Bau Bang district’s Tru Van Tho commune in Binh Duong province and ending at Km41+150, adjacent to the Construction Package No. 2 in Trang Bang district’s Hung Thuan commune in Tay Ninh Province. The total length of the route under this package is approximately 31.15 kilometers, with a total contract value of VND 681.84 billion.

Pham Van Hung, Deputy General Director of Deo Ca Group, the contractor for this package stated that the roadbed has been basically completed. Currently, the construction of various sub-base layers is underway, covering 30 out of 31 kilometers and asphalt pavement has been completed on nearly 21 kilometers. The overall progress of the package has reached 70% of the contract value. Deo Ca Group is making great efforts to overcome obstacles and is determined to open the entire route to technical traffic in time for the 50th anniversary of the Liberation of the South and National Reunification (April 30, 1975 – April 30, 2025), shortening the schedule by seven months compared to the original contract.

 Reported by Minh Duy-Cong Khanh-Translated by Kim Tin

Tags: Bau Bang

Green development under local characteristics

With various industrial parks (IPs) already built or planned for future investment, Bau Bang district has identified green industry as its strategic path

Vietnamese products grab spotlight at Algiers int’l fair 2025

Vietnamese goods are gaining international attention at the 56th Algiers International Fair (FIA 2025), held from June 23–28 in Algeria's capital.

OCOP programme hits milestone with 126 five-star products nationwide

The National Council for the Evaluation of OCOP Products on Tuesday announced the recognition of 47 new five-star-rated products under the One Commune One Product (OCOP) programme,

In-depth industrial development

In the first six months of 2025, the Index of Industrial Production (IIP) in Binh Duong province is estimated at increasing by 10.19% compared to the same period last year.

In-depth industrial development

In the first six months of 2025, the Index of Industrial Production (IIP) in Binh Duong province is estimated at increasing by 10.19% compared to the same period last year.

Establishing a framework for the reorganization of the global supply chain

In light of the global economy being influenced by various factors such as supply chain disruptions,

Opening doors for workers to own housing

With the strong support of the government, active participation from the banking system, and the attention of provincial leaders and businesses, access to social housing for workers and low-income individuals is widening.

Tan Uyen city enhances the inspection and enforcement of trade violations

In accordance with the directives of the Provincial Steering Committee for the Prevention of Smuggling, Trade Fraud,

Total tax revenue in Binh Duong reaches 63.7% of estimate

On June 23, Tax Department of Region XVI held a conference to review tax work for the first six months of 2025, outline tasks for the remaining six months, and honor exemplary enterprises.

Elevating development

Amid the current global economic landscape, which is being significantly impacted by shifts in supply chains, trade dynamics

Enterprise - Brand

Company Social Media Net

Company VIETNAMNAY

Company HANEL MIROLIN

Company Keangnam - vina

Company HP Travel

Company Keloph