The year 2020 is the last year of the medium-term public investment plan 2016-2020. The completion of key projects has an important meaning in ensuring the fulfillment of the public investment plan for the term, and at the same time creates dynamism. In order to ensure economic growth, successfully implement the socio-economic development targets (Socio-Economic) in 2020, especially in the context of heavily affected by the Covid-19 epidemic.
Motivation for development
Determining the transport infrastructure must be one step ahead, so the province has focused on investing in technical infrastructure system with many economic resources, to meet the overall development needs of the province. Many key constructions with inter-regional and inter-provincial connections have been invested, built and made important contributions to local economic development.

The completion of key projects contributes to the motivation for economic growth. In the photo: The construction of the 1,500-bed General Hospital is being accelerated to complete in 2020
The route from Muoi Muoi crossroads to Tan Thanh junction is the synchronous connection of transport infrastructure between Tan Uyen center and Bac Tan Uyen district, passing Dat Cuoc Industrial Park, connecting to the North route of Tan Uyen - Phu Giao - Bau Bang, Thu Bien - Dat Cuoc. The project has a length of more than 10,220m, including 5 packages for road construction, 1 package for electrical relocation and 1 package for construction of lighting system. The route is designed according to the standard of grade III, with 6 lanes and a total investment of more than 764,480 billion VND from the State budget. Up to now, bidding packages No. 2, 3, 4, 5 and 6 have been completed and put into use. Package 1 has completed 1,500m above 2,000m in length, 500m is waiting for ground for construction. It is expected that in September 2020 this package will be completed and put into use,
The project to build embankments against landslide along Dong Nai river from Rach Tre bridge to Thi uy TX.Tan Uyen has been constructing a lot of significance for local socio-economic development. The project is invested by the Provincial Construction Investment Project Management Unit, belonging to a type-III irrigation project. The project has a design scale of 3 sections with a total length of 660m, total construction investment of VND 200.6 billion. Currently, the first phase of the project has been completed and put into use. Mr. Doan Hong Tuoi, Chairman of People's Committee of Tan Uyen Town, said that the first phase of the project was completed, the local leaders and people of Tan Uyen Town were very happy. The work is not only meaningful to prevent river bank erosion but also contribute to urban embellishment, which is a highlight of the landscape of Tan Uyen Town. In addition, the work contributes to environmental protection, facilitate regional transportation and contribute to changing the living conditions of the people in the best way. Currently, the second phase of the project is being accelerated by the construction unit.
Besides focusing on investing in economic and technical infrastructure, Binh Duong also pays special attention to social infrastructure investment, especially health infrastructure. As one of the key projects, the 1,500-bed General Hospital project has a total construction investment of more than 2,318 billion dong. The construction of a 1,500-bed General Hospital will create favorable conditions for the provincial health sector to further improve the quality of people's health care, well solve the need for medical examination and treatment of people in the province and the region and create a new face for Binh Duong urban area.
Mr. Ta Viet Hung, Project Management and Technical Director of Construction Corporation No. 1-JSC said, so far, the construction unit has made a fairly large amount, basically meeting the required progress of investor's demand. Package 1 has basically completed the rough work, installed the M&E system, accounting for 38.5% of the contract volume. Package No.2 installed copper pipes with medical gas system, accounting for 10% of the volume.
Reportedly, Package 1 of the 1,500-bed General Hospital project was started on December 4, 2018, the construction time is 520 days, and the completion time is on May 7, 2020. Package 2 commences on April 23, 2019, constructing and installing medical gas systems and transporting patient samples. Talking to the reporter, Mr. Nguyen Chi Duc, Director of the Provincial Construction Investment Project Management Board, said that in the coming time, he will continue to coordinate with the construction and supervision unit to speed up the next progress.
Accelerate progress
2020 is the last year of the medium-term public investment plan 2016-2020. Therefore, the provincial leaders pay great attention and focus to the completion of key projects and projects as planned. According to the Provincial Construction Investment Project Management Board, in the first quarter of 2020, the implemented volume in the period is VND 42,978 billion, the cumulative volume to date is VND 135.052 billion, reaching 3.25%.
In order to complete the plan for the implementation of key projects in 2020, the provincial People's Committee has developed and implemented an action plan to remove difficulties for production, business, and ensure social security to respond to Covid disease. -19 in Binh Duong province. In which, focusing on speeding up the implementation and disbursing investment capital. Accordingly, the Provincial People's Committee requires departments, agencies, and People's Committees of districts, towns and cities to focus on directing and soon completing and putting into use large and important infrastructure works, maximizing their promotion, design capacity, socio-economic efficiency. Besides, regularly checking, taking measures to remove difficulties and obstacles to ensure the progress, volume and quality of the work. The provincial People's Committee also requested the Department of Transport to urgently complete procedures and promoting disbursement, implementing important transport projects, have spillover effects.
Reported by Phuong Le – Translated by Vi Bao