In 2015, Binh Duong Provincial Construction Management Authority has been assigned by local People’s Committee the management of 56 projects funded by the provincial budget. Of the projects, 23 are under construction and 4 are under bidding process.
Mr. Nguyen Duc Chinh, Deputy Director of the Authority, informed that by March 16, VND 406.381 billion has been used for the projects, covering 28.62% of the progress. The capital allocation was VND 540.591 billion or 39% of the year plan.
Reported by P. Le – Translated by Vi Bao